Year : 2015

In Phase # 1 of New Giza University TECO was Selected by the Client among other Competitors to be the ELV Contractor for Buildings (A), (B), and Utility Building Where TECO executed the first fix, Second Fix and Third fix for Structured Cabling, Fire Alarm, Sound System, and Master Clock System. After Client’s selection TECO was the ELV nominated contractor to EL - OFOQ. TECO spent a lot of efforts to catch up with the project schedule specially the selection of TECO was made after most of construction works were done

In Phase # 2 of New Giza University, although TECO did not participate as ELV Contractor, El - OFOQ who was awarded other two buildings in the university selected TECO to be the supplier of the Fire Alarm System and do the connection with the fire alarm system in phase # 1

 

 Main Contractor:  Al Rowad

 MEP Contractor:El - OfOQ

       
   
 

 TECO Scope of Work

  • Supply and Installation of Structured Cabling
  • Fire Alarm
  • Public Address
  • Master Clock system

complete with Networks and all related first fix (Conduits, Cable Trunks, Back boxes)

 
 

 

NGU External View

Structured Cabling Racks

Main Fire Alarm Control Pane

NGU – Slave Clocks in corridors and Public Areas

 NGU – Public Address Racks

NGU – Main Entrance Hall

NGU – Lecture Hall

NGU – Class Room

NGU – Waiting Area

NGU – Corridor